Sunday, 28 Dec 2025
  • About Us
  • Contact Us
  • Terms and Conditions
  • Privacy Policy
Subscribe
Life Care News
  • Home
  • Business
    • Business Wire
    • Globenews Wire
  • News
    NewsShow More
    Confidence Surges Among Small Enterprises Despite Global Headwinds, Reflecting India’s Strong Economic Momentum – ASSOCHAM Dun & Bradstreet Small Business Confidence Index
    Confidence Surges Among Small Enterprises Despite Global Headwinds, Reflecting India’s Strong Economic Momentum – ASSOCHAM Dun & Bradstreet Small Business Confidence Index
    27/12/2025
    Bybit’s Yoyee Wang Says Capital-Efficient Custody and Regulatory Clarity Are Key to Institutional Crypto Adoption
    Bybit’s Yoyee Wang Says Capital-Efficient Custody and Regulatory Clarity Are Key to Institutional Crypto Adoption
    27/12/2025
    What Hebei Can OfferThe Photovoltaic Miracle of Ningjin
    26/12/2025
    Fermenta Ranked Among India’s Best Workplaces in Pharmaceuticals, Healthcare & Biotech by Great Place to Work
    Fermenta Ranked Among India’s Best Workplaces in Pharmaceuticals, Healthcare & Biotech by Great Place to Work
    26/12/2025
    Safe & Secure Cities theme takes centre stage at Municipalika 2026
    Safe & Secure Cities theme takes centre stage at Municipalika 2026
    25/12/2025
  • Tech
  • Health
  • Sports
  • Entertainment
  • Automobile
  • 🔥
  • news
  • global
  •  and
  •  the
  • announced
  • today
  • Business
  • Tech
  •  for
  • will
Font ResizerAa
Life Care NewsLife Care News
  • Home
  • Business
  • News
  • Tech
  • Health
  • Sports
  • Entertainment
  • Automobile
Search
  • Home
  • Business
    • Business Wire
    • Globenews Wire
  • News
  • Tech
  • Health
  • Sports
  • Entertainment
  • Automobile
Follow US
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Tech

Bitdeer Announces August 2025 Production and Operations Update

GlobeNews Wire
Last updated: 12/09/2025 5:31 PM
GlobeNews Wire
Share
12 Min Read
Bitdeer Announces August 2025 Production and Operations Update
SHARE
Bitdeer Announces August 2025 Production and Operations Update

–  Increased self-mining hashrate by 35% to 30.0 EH/s on continued deployment of SEALMINERs

SINGAPORE, Sept. 12, 2025 (GLOBE NEWSWIRE) — Bitdeer Technologies Group (NASDAQ: BTDR) (“Bitdeer” or the “Company”), a world-leading technology company for Bitcoin mining, today announced its unaudited mining and operations updates for August 2025.

Operational Update

  • Self-mined Bitcoin: 375 Bitcoins, an increase of ~33% from July 2025 due to higher average self-mining hashrate from energization of SEALMINERs.
  • Mining Rig Manufacturing and R&D:
    • SEALMINER A1: 4.1 EH/s have been energized.
    • SEALMINER A2:
      • Total of 27.8 EH/s in mining rigs have been manufactured and an additional 1.2 EH/s are in final assembly as of end of August 2025.
      • Of the 27.8 EH/s mining rigs that have been manufactured:
        • External-sales: 6.0 EH/s of mining rigs have been shipped to external customers, including 0.1 EH/s that were shipped in August.
        • Self-mining:
          • 18.0 EH/s of mining rigs have been deployed in U.S., Tydal, Norway and Jigmeling, Bhutan, including 7.8 EH/s in August 2025.
          • 2.7 EH/s of mining rigs are in-transit to Bitdeer’s sites in Norway and Bhutan.
          • 1.1 EH/s of mining rigs are being prepared for shipping.
    • SEALMINER A3:
      • In final stages of preparation for mass production which is expected to begin in late September or early October.
      • Machine level testing results meeting expectations.
      • The specific machine models and specifications will be announced alongside mass production.
    • SEALMINER A4:
      • On track to achieve an expected chip efficiency of approximately 5 J/TH.
      • Planning two different chip designs of SEAL04 to ensure success.
    • U.S. Manufacturing: Bitdeer’s U.S. factory is actively in planning and preparation.
  • HPC/AI:
    • Entered into advanced negotiations with a development partner regarding Clarington, Ohio site.
    • Bitdeer.AI, the Company’s neo cloud business, reached US$8 million AI cloud ARR (annualized run-rate revenue) in August from providing GPU cloud services, with significant growth expected from Q4 2025.
    • 8 NVL72 servers are being installed in Malaysia and are expected to start serving customers in Q4 2025.
    • Successfully launched Relational Database Service (RDS). Actively developing AI Agent and Retrieval-Augmented Generation (RAG) technologies to enhance knowledge base and AI cloud services.
    • Investigating deployment of modular data centers at Wenatchee, Washington facility.
  • Hosting:
    • The hosted hash rate remained unchanged in August 2025.
  • Infrastructure:
    • Tydal, Norway (Hydro): 161 MW is online. The remaining 14 MW is expected to be energized by the end of Q3 2025.
    • Jigmeling, Bhutan: 367.5 MW is online, with the remaining 132.5 MW expected to be energized in phases by the end of Q3 2025.

Management Commentary

“Our operational team continues to execute and we are well on our way to achieving our ambitious target of 40 EH/s of self-mining by the end of October 2025.” said Matt Kong, Chief Business Officer at Bitdeer. “However, we’re not stopping there. Over the coming quarters, we will continue expanding our SEALMINER fleet into our near-term global power capacity, putting us on track to become one of the largest vertically integrated miners in the world.”

Production and Operations Summary

Metrics August 2025 July 2025 August 2024
Total hash rate under management1 (EH/s) 44.2 36.4 16.8
– Proprietary hash rate 30.3 22.5 8.6
• Self-mining 30.0 22.3 7.8
• Cloud Hash Rate – – 0.8
• Delivered but not hashing 0.3 0.2 –
– Hosting 13.9 13.9 8.2
Mining rigs under management 229,000 213,000 167,000
– Self-owned2 143,000 127,000 87,000
– Hosted 86,000 86,000 80,000
Bitcoins mined (self-mining only) 375 282 166
Bitcoin held3 1,934 1,667 290
1 Total hash rate under management as of August 31, 2025 across the Company’s primary business lines: Self-mining, Cloud Hash Rate, and Hosting.
• Self-mining refers to cryptocurrency mining for the Company’s own account, which allows it to directly capture the high appreciation potential of cryptocurrency.
• Cloud Hash Rate offers hash rate subscription plans and shares mining income with customers under certain arrangements. The Cloud Hash Rate stated above reflects the contracted hash rate with customers at month-end.
• Hosting encompasses a one-stop mining machine hosting solution including deployment, maintenance, and management services for efficient cryptocurrency mining.
2 Self-owned mining machines are for the Company’s self-mining business and Cloud Hash Rate business.
3 Bitcoins held do not include the Bitcoins from deposits of the customers.
 

Infrastructure Construction Update

Site / Location Capacity (MW) Status Timing4
Electrical capacity      
– Rockdale, Texas 563 Online Completed
– Knoxville, Tennessee 86 Online Completed
– Wenatchee, Washington 13 Online Completed
– Molde, Norway 84 Online Completed
– Tydal, Norway 211 Online Completed
– Gedu, Bhutan 100 Online Completed
– Jigmeling, Bhutan 367.5 Online Completed
Total electrical capacity 1,424.55    
Pipeline capacity      
– Tydal, Norway 14 In progress Q3 2025
– Massillon, Ohio 221 In progress Q1 2026
– Clarington, Ohio 570 In progress Q2 2027
– Jigmeling, Bhutan 132.5 In progress Q3 2025
– Rockdale, Texas 179 In planning Estimate 2026
– Alberta, Canada 99 In planning Q4 2026
– Oromia Region, Ethiopia 50 In progress Q4 2025
Total pipeline capacity 1,265.5    
Total global electrical capacity 2,690    
4 Indicative timing. All timing references are to calendar quarters and years.
5 Figures represent total available electrical capacity.
 

Rockdale, Texas – 100 MW Hydro-cooling conversion has been fully energized.

Tydal, Norway – 175 MW site expansion has commenced energization and the full energization timeline has been adjusted to the end of Q3 2025:

  • 161 MW is online.
  • All equipment has been delivered. The remaining 14 MW is expected to be energized by the end of Q3 2025.

Massillon, Ohio – 221 MW site is under construction and the full energization timeline has been adjusted to the end of Q1 2026 due to transformer delivery delays, labor storages and anticipated cold winter months:

  • 21MW is expected to be energized by the end of October 2025. 
  • The remaining 200MW is expected to be energized in phases by the end of Q1 2026.

Clarington, Ohio – 570 MW under contract – power and datacenter infrastructure to be completed in Q2 2027.

Jigmeling, Bhutan – 500 MW site has commenced energization and is expected to be fully energized in phases by the end of Q3 2025:

  • 367.5 MW is online.
  • The remaining 132.5 MW is expected to be energized in phases by the end of Q3 2025.
  • Two 132kV transformers and five 220kV transformers have been energized in June 2025.
  • Delivery of containers and hydro-cooling systems have been completed and are now being installed.

Fox Creek, Alberta – 101 MW site acquired in Alberta, is fully licensed and permitted to construct an on-site natural gas power plant. The project is expected to be energized by the end of Q4 2026.

Oromia Region, Ethiopia – SPA and a turnkey agreement signed for the acquisition and construction of a 50 MW Bitcoin mining project in Ethiopia. The project is expected to be energized in Q4 2025.

Upcoming Conferences and Events

  • October 7, 2025: CEO Summit in Phoenix
  • November 10 – 12, 2025: Cantor Crypto, AI/Energy Infrastructure Conference in Miami
  • January 13 – 16, 2026: 28th Annual Needham Growth Conference in New York

About Bitdeer Technologies Group

Bitdeer is a world-leading technology company for Bitcoin mining. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers. Bitdeer handles complex processes involved in computing such as equipment procurement, transport logistics, datacenter design and construction, equipment management, and daily operations. Bitdeer also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed datacenters in the United States, Norway, and Bhutan. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X @ BitdeerOfficial and LinkedIn @ Bitdeer Group.

Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on the social media and other communication channels listed on its website.

Forward-Looking Statements

Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute “forward-looking statements” within the meaning of The Private Securities Litigation Reform Act of 1995. The words “anticipate,” “look forward to,” “believe,” “continue,” “could,” “estimate,” “expect,” “intend,” “may,” “plan,” “potential,” “predict,” “project,” “should,” “target,” “will,” “would” and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled “Risk Factors” in Bitdeer’s annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer’s subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.

For investor and media inquiries, please contact:

Investor Relations
Orange Group
Yujia Zhai
bitdeerIR@orangegroupadvisors.com

Media
Elev8 New Media
Jessica Starman, MBA
bitdeer@elev8newmedia.com

Public Relations
BlocksBridge Consulting
Nishant Sharma
bitdeer@blocksbridge.com

CMSI PARTNERS ANNOUNCE THE FINAL PUBLIC CONSULTATION FOR THE CONSOLIDATED MINING STANDARD TO START ON 8 OCTOBER 2025
Robert Lewandowski Named Global Brand Ambassador for KSM-66 Ashwagandha
Hyundai CRADLE Partners with UNCAGED Innovations to Develop Sustainable Leather Alternatives for Vehicles
CCTV4: Heritage and Harmony Beneath the Full Moon, The World Is Invited to the CMG 2025 Mid-Autumn Festival Gala
ACES India and BSNL Partner to Power 4G and 5G Connectivity on Mumbai Metro Aqua Line-3
TAGGED: and2025announcedannouncesaugustbitcoinbitdeerbtdrcompanycontinueddeploymentehsglobegrouphashrateincreasedKYG114481008miningnasdaqNasdaq:BTDRnewsnewswireoperationaloperationsproductionsealminersselfminingseptsingaporetechnologiesTechnologytodayunauditedupdateupdatesworldleading
Share This Article
Facebook Copy Link Print
- Advertisement -

Your Trusted Source for Accurate and Timely Updates!

Our commitment to accuracy, impartiality, and delivering breaking news as it happens has earned us the trust of a vast audience. Stay ahead with real-time updates on the latest events, trends.
FacebookLike
XFollow
PinterestPin
InstagramFollow
YoutubeSubscribe
LinkedInFollow
MediumFollow

Most Selling Products

Top Picks, Trending Now – Discover the Best Sellers!
Tecno Camon 20 Premier 5G

Tecno Camon 20 Premier 5G

Dark Welkin | 8GB RAM + 512GB Storage (Expandable RAM up to 16GB) | Industry’s 1st 50MP RGBW-Pro Camera | Segment-First 108MP Ultra-Wide Macro Lens | 6.67" 120Hz 10-bit AMOLED In-Display

iQOO Z10 Lite 5G

iQOO Z10 Lite 5G

Titanium Blue | 6GB RAM + 128GB Storage | Dimensity 6300 5G with 433K+ AnTuTu Score | Robust 6000mAh Battery | IP64 Rated + Military-Grade Shock Resistance

OnePlus 13s

OnePlus 13s

Black Velvet | 12GB RAM + 256GB Storage | Flagship Snapdragon® 8 Elite Chipset | Exceptional Battery Life in a Compact Form | Lifetime Display Warranty Included

Samsung Galaxy A55 5G

Samsung Galaxy A55 5G

Awesome Iceblue | 8GB RAM + 256GB Storage | Premium Metal Frame | 50MP OIS Main Camera with Nightography | IP67 Water & Dust Resistance | Gorilla Glass Victus+ | sAMOLED Display with Vision Booster

You Might Also Like

Milano Cortina 2026 and On Location unveil exclusive hospitality packages for the Olympic Winter Games

06/07/2025
Dhruva Advisors Unveils Second Edition of 'Investing in India 2025': A Comprehensive Guide for Global Investors
Business

Dhruva Advisors Unveils Second Edition of 'Investing in India 2025': A Comprehensive Guide for Global Investors

23/10/2025
JK Tech Appoints Vijai Ganesh as Chief Delivery Officer to Strengthen Global Delivery Excellence
Tech

JK Tech Appoints Vijai Ganesh as Chief Delivery Officer to Strengthen Global Delivery Excellence

27/07/2025
RiverMeadow Expands Global Reach with Launch in AWS Asia Pacific (Taipei) Region
Tech

RiverMeadow Expands Global Reach with Launch in AWS Asia Pacific (Taipei) Region

11/06/2025
Life Care News
Facebook Twitter Youtube Rss Medium

Life Care News:


We increase the awareness of millions of users through our news networks. We are one of the most trusted news networks in the world.

Top Categories
  • Home
  • Business
  • News
  • Tech
  • Health
  • Sports
  • Entertainment
  • Automobile
Usefull Links
  • About Us
  • Contact Us
  • Terms and Conditions
  • Privacy Policy
Copyright © 2015 – 2025 LifeCareNews Network. All Rights Reserved. LIFE CARE IS REGISTERED MAGAZINE IN RNI, NO.GUJGUJ/2015/71283
Life Care NewsLife Care News
Copyright © 2015 - 2025 LifeCareNews Network. All Rights Reserved. LIFE CARE IS REGISTERED MAGAZINE IN RNI, NO.GUJGUJ/2015/71283
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?